GROUP: |
Mechanical |
TYPE: |
Plumbing |
SUB-TYPE: |
Commercial |
PRIMARY USE: |
N/A |
WORK DESCRIPTION: |
PLUMBING TENANT IMPROVEMENT FOR A NEW L. A. FITNESS CENTER LOCATED IN A METHANE BUFFER ZONE. |
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
05/18/2012 |
ISSUING OFFICE: |
Metro |
CURRENT STATUS: |
Permit Finaled |
CURRENT STATUS DATE: |
02/12/2013 |
|
|
Submitted |
12/16/2011 |
APPLICANT |
Assigned to Plan Check Engineer |
01/26/2012 |
BRYAN GAVIDIA |
Corrections Issued |
02/08/2012 |
BRYAN GAVIDIA |
Quality Review Completed |
02/14/2012 |
WILBERT GUERRERO |
Mechanical Plans Picked Up |
02/24/2012 |
APPLICANT |
Plan Check Approved |
05/18/2012 |
MANUEL HERNANDEZ |
Plan Check Approved |
05/18/2012 |
KRISANDRA TORRES |
Issued |
05/18/2012 |
LADBS |
Permit Finaled |
02/11/2013 |
GUS MCBEATH |
|